Our team at Hassan Allam Construction celebrated the successful operation of the first turbine in the New Simple Cycle Al Arish Power Plant, connecting it to the national grid. This complex project saw HAC dismantle, ship, install, and start up General Electric built turbines in record time and in challenging work conditions. The 2 × 125 MW simple cycle power plant project includes engineering, procurement and construction works on the Al Arish power plant site, with dismantling and transportation works on the Damietta power plant site. In addition, the scope of work includes installation, testing, commissioning, operation, and maintenance. The project demonstrates Hassan Allam Construction’s capabilities to deliver complex projects in adherence to the highest international quality and health and safety standards.